Development review · Planning application
Commercial building approved on nearly 2-acre site in Meridian
The city approved design review and a zoning compliance certificate for a new commercial building by Dave Evans Construction, and the project has since been finaled. The site covers 1.94 acres and was filed April 18, 2025.
About this application
New commercial construction built by Dave Evans Construction. Parcels will be R9010680121 and R9010680131. See narrative for more info.
Project name on file: Cortona Way Retail Bldg. B
Timeline
June 27, 2025
MFD Plan Review: Approved
June 6, 2025
MFD Plan Review: More Information Required
May 30, 2025
Planning Review: Approved
May 5, 2025
MFD Plan Review: More Information Required
April 25, 2025
Wastewater Modeling Review: Approved
April 25, 2025
Planning Review: More Information Required
April 22, 2025
Transportation Plan Review: No Comment
April 22, 2025
Land Development Review: Approved
April 21, 2025
ACHD Review: Approved
April 21, 2025
Water Modeling Review: Approved
April 21, 2025
MPD Review: Approved
April 21, 2025
GIS Review: Approved
April 18, 2025
Floodplain Review: FLDP Not Required
April 18, 2025
Application Submittal: Accepted
April 18, 2025
Application filed
Documents