Tesla plans eight EV charging stations in Winco parking lot, approved

The city has finalized approval for a commercial site with eight electric vehicle charging posts, a Supercharger unit, a payment kiosk, two light poles and related utility equipment. No homes are involved.

ApprovedA-2026-0004Filed Jan. 20, 2026East Meridian · 1050 Progress
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

Tesla is proposing to install (8) electric vehicle (EV) charging stations, associated ground equipment ((1) pad mounted utility transformer, (1) 1600A 277/480V switchboard, (1) Tesla Pre-assembled Supercharger unit (with (1) V4 Supercharger cabinet and (8) V4 charge posts), (2) light poles and (1) payment kiosk.

Project name on file: Tesla EV Charging Stations (Winco Parking Lot)

Timeline

  1. March 3, 2026

    Transportation Plan Review: No Comment

  2. Feb. 27, 2026

    MPD Review: No Comment

  3. Feb. 25, 2026

    MFD Plan Review: Approved

  4. Feb. 24, 2026

    Planning Review: Approved

  5. Feb. 23, 2026

    Water Modeling Review: Approved

  6. Feb. 23, 2026

    MPD Review: Approved

  7. Feb. 23, 2026

    Land Development Review: Approved

  8. Feb. 21, 2026

    Wastewater Modeling Review: Approved

  9. Feb. 20, 2026

    Floodplain Review: FLDP Not Required

  10. Feb. 20, 2026

    ACHD Review: Approved

  11. Feb. 20, 2026

    GIS Review: Approved

  12. Feb. 20, 2026

    Application Submittal: Accepted

  13. Jan. 20, 2026

    Application Submittal: More Information Required

    Good morningPlease upload files per submittal standards. Unless a planner advised of documents not needed for review.Recorded warranty deed for the subject property Warranty DeedScaled vicinity map showing the location of the subject property Vicinity Map*Photometric PlanSubmit PDF copy of the conceptual engineering plans in the format specified above. *Public Utility PlanElevationsLandscape PlanCopy of the recorded plat the property lies within (8 ½” x 11”) Recorded Plat1 page pdf named in drawings folder

  14. Jan. 20, 2026

    Application filed

Documents

No documents have been published for this record yet.