Development review · Planning application
Tesla plans eight EV charging stations in Winco parking lot, approved
The city has finalized approval for a commercial site with eight electric vehicle charging posts, a Supercharger unit, a payment kiosk, two light poles and related utility equipment. No homes are involved.
About this application
Tesla is proposing to install (8) electric vehicle (EV) charging stations, associated ground equipment ((1) pad mounted utility transformer, (1) 1600A 277/480V switchboard, (1) Tesla Pre-assembled Supercharger unit (with (1) V4 Supercharger cabinet and (8) V4 charge posts), (2) light poles and (1) payment kiosk.
Project name on file: Tesla EV Charging Stations (Winco Parking Lot)
Timeline
March 3, 2026
Transportation Plan Review: No Comment
Feb. 27, 2026
MPD Review: No Comment
Feb. 25, 2026
MFD Plan Review: Approved
Feb. 24, 2026
Planning Review: Approved
Feb. 23, 2026
Water Modeling Review: Approved
Feb. 23, 2026
MPD Review: Approved
Feb. 23, 2026
Land Development Review: Approved
Feb. 21, 2026
Wastewater Modeling Review: Approved
Feb. 20, 2026
Floodplain Review: FLDP Not Required
Feb. 20, 2026
ACHD Review: Approved
Feb. 20, 2026
GIS Review: Approved
Feb. 20, 2026
Application Submittal: Accepted
Jan. 20, 2026
Application Submittal: More Information Required
Good morningPlease upload files per submittal standards. Unless a planner advised of documents not needed for review.Recorded warranty deed for the subject property Warranty DeedScaled vicinity map showing the location of the subject property Vicinity Map*Photometric PlanSubmit PDF copy of the conceptual engineering plans in the format specified above. *Public Utility PlanElevationsLandscape PlanCopy of the recorded plat the property lies within (8 ½” x 11”) Recorded Plat1 page pdf named in drawings folder
Jan. 20, 2026
Application filed