Design review · Planning application

2,875-square-foot addition to sewer plant blower building approved

Eagle City Council approved the single-story addition, about 24 feet tall, on Feb. 25 on its consent agenda. It would bring the blower building to 8,829 square feet. Conditions include landscape screening of ground-mounted utility boxes.

ApprovedDR-2016-69-MOD1State Street Corridor · 100 South Urban Gate Avenue
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

The Eagle Sewer District wants to add a 2,875-square-foot addition to its existing blower building at its wastewater treatment facility at 100 South Urban Gate Avenue. The addition would be a single-story building about 24 feet tall, matching the look of the existing buildings, bringing the blower building to 8,829 square feet total. The Design Review Board approved it with conditions.

Eagle Sewer District, represented by Walter Lindgren with Lindgren Labrie Architecture, PLLC, is requesting design review approval of a 2,875-square foot building addition to the blower building for the Eagle Sewer District. The 33.94-acre site is located on the southeast corner of South Urban Gate Avenue and State Highway 44 at 100 South Urban Gate Avenue.

Project name on file: Building Addition to the Eagle Sewer District Blower Building

Timeline

  1. Feb. 25, 2025

    Approved

    Eagle City Council: Approved on its consent agenda.

Documents

Staff reports

Decisions

  • Findings of fact and conclusions of law

    Eagle Design Review Board decision on the Eagle Sewer District's request for a 2,875-square foot addition to its blower building, heard January 23, 2025.

    Feb. 12, 2025 · 11 pages · Decision

Nearby

The Boise Builds daily briefing

Every new planning application in Boise, Meridian, Nampa, Caldwell and Eagle, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.