Annexation · Planning application

74-home subdivision with commercial land approved on 77 acres in Meridian

The approved plan annexes 77.33 acres into the city, with about 22 acres zoned residential and 55 acres commercial. A preliminary plat covers 75 building lots on 71.3 acres, for residential, office, commercial and employment uses. The city decided July 9, 2019.

ApprovedH-2019-0021Filed Feb. 7, 2019Meridian+4 related filings
Pin at the reported location.

About this application

AZ of 77.33 acres of land with R-8 (21.95 acres) & C-G (55.38 acres) zoning districts; Preliminary Plat consisting of 75 building lots, 7 common lots and 3 other lots on 71.3 acres of land in the R-8 and C-G zoning districts

Project name on file: Pollard Subdivision

Timeline

  1. Oct. 15, 2019

    GIS Final Review: Entered In GIS

  2. July 9, 2019

    Public hearing: Meridian City Council

    Outcome: Approved.

  3. July 9, 2019

    Decision: Approved

    Meridian City Council: Approved.

  4. June 5, 2019

    Final Action: Application Complete

    Findings Signed on 6-4

  5. June 4, 2019

    Public hearing: Meridian City Council

    Outcome: Approved.

  6. June 4, 2019

    Decision: Approved

    Meridian City Council: Approved.

  7. May 22, 2019

    City Council Hearing: Approved

  8. May 21, 2019

    Public hearing: Meridian City Council

    Outcome: FF-CL Requested for Approval.

  9. May 21, 2019

    Decision: FF-CL Requested for Approval

    Meridian City Council: FF-CL Requested for Approval.

  10. April 19, 2019

    Planning and Zoning Hearing: Recommend Approval

  11. April 18, 2019

    Public hearing: Meridian Planning and Zoning Commission

    Outcome: Recommended Approval.

  12. April 18, 2019

    Recommended Approval

    Meridian Planning and Zoning Commission: Recommended Approval.

  13. April 4, 2019

    Parks Review: No Comment

  14. March 21, 2019

    Public hearing: Meridian Planning and Zoning Commission

  15. March 21, 2019

    Community Development Review: Staff Recommend Approval w/ Cond

  16. March 13, 2019

    MPD Review: Review Complete

    See attached police comments.

  17. Feb. 25, 2019

    MFD Plan Review: Review Complete w/ Cond

    Comments uploaded to Accela and emailed to Sonya.

  18. Feb. 22, 2019

    Water Modeling Review: Review Complete

    See Engineering-Water Staff Report Comments

  19. Feb. 22, 2019

    Transportation Plan Review: Review Complete w/ Cond

    A street light plan will need to be included in the final plat application. Street light plan requirements are listed in section 6-7 of the City's Design Standards.

  20. Feb. 21, 2019

    GIS Review: Review Complete

  21. Feb. 20, 2019

    Reclaimed Water Review: Reclaimed Water Modeling NOT Required

  22. Feb. 20, 2019

    Floodplain Review: FLDP Not Required

  23. Feb. 20, 2019

    Transmit and Notice: Distribute for Plan Review

  24. Feb. 20, 2019

    Legal Description Review: Verified Legal Description

    Correction was made and a new copy of the C-G description was obtained. I removed those pages from the original AZ Exhibit and added the 3 new pages and uploaded it. We should be good to go.

  25. Feb. 20, 2019

    Planning Cursory Review: Return to Plan Intake

  26. Feb. 20, 2019

    Plan Intake: Application Submitted

  27. Feb. 20, 2019

    Plan Intake: Accepted

  28. Feb. 19, 2019

    Wastewater Modeling Review: Review Complete

    See Staff Report_WW_Comments

  29. Feb. 14, 2019

    Legal Description Review: More Information Required

    This mostly looks excellent. It has one bearing on a map that has the wrong direction on it. I have added a document titled COGO_error that illustrates the problem.

  30. Feb. 13, 2019

    Reclaimed Water Review: Reclaimed Water Modeling NOT Required

  31. Feb. 13, 2019

    GIS Cursory Review: Entered in GIS

  32. Feb. 13, 2019

    Plan Intake: Cursory Review

  33. Feb. 8, 2019

    Plan Intake: Application Incomplete

    Need AutoCAD file so the project can be modeled by PW. Notified applicant on 02/08/2019.

  34. Feb. 7, 2019

    Reclaimed Water Review: Reclaimed Water Modeling NOT Required

  35. Feb. 7, 2019

    Plan Intake: Application Submitted

  36. Feb. 7, 2019

    Application filed

Documents

Other documents

  • Email Confirmation Final Action Courtesy Letter

    June 17, 2019 · 518 KB · Viewable by All

  • Revised Sewer Layout showing lift station on site

    March 20, 2019 · 1.4 MB · Viewable by All

  • Police Comments

    March 13, 2019 · 158 KB · Viewable by All

  • Police Comments

    March 13, 2019 · 44 KB · Viewable by All

  • Engineering-Water Staff Report Comments

    Feb. 22, 2019 · 13 KB · Viewable by All

  • Application

    Feb. 20, 2019 · 73.8 MB · Viewable by All

  • AZ Exhibit With Revised C-G

    Feb. 20, 2019 · 2.7 MB · Viewable by All

  • Staff Report_WW_Comments

    Feb. 19, 2019 · 9 KB · Viewable by All

  • COGO_error

    Feb. 14, 2019 · 334 KB · Viewable by All

  • Autocad file

    Feb. 13, 2019 · 4.9 MB · Viewable by All

  • Elevations

    Feb. 8, 2019 · 1.4 MB · Viewable by All

  • Engineering Plans

    Feb. 8, 2019 · 2.4 MB · Viewable by All

  • Landscape Plan

    Feb. 8, 2019 · 5.2 MB · Viewable by All

  • Open Space Exhibit

    Feb. 8, 2019 · 754 KB · Viewable by All

  • Pre-plat

    Feb. 8, 2019 · 2.9 MB · Viewable by All