Skip to content

Rezone · Planning application

City approves rezoning and 83-lot plan for 132-acre mixed-use area with 75 homes

Meridian approved a single master development agreement, rezoning for commercial and high-density residential use, and a plat with 83 buildable lots on 132.42 acres. The decision came after a June 8, 2021, hearing.

ApprovedH-2020-0074Filed June 16, 2020Meridian+1 related filing
Pin at the reported location.

About this application

MDA to replace all existing DA's in the TM Crossing area with one Master DA with project specific design guidelines; Rezone of 40.98 from R-40 & C-C to C-G, 3.9 from TN-C & C-G to R-40, 0.65 from R-8 & TN-C to C-G and 0.53 from TN-C to C-G; and PP for 83 buildable lots & 2 common on 132.42 acres. S1214120661; S1214120710; S1214121133; S1214121134; S1214121172; S1214212580; S1214212622; S1214212742; S1214120631; S1214212805; S1214212822; S1214233668; S1214234021; S1214233680

Project name on file: Ten Mile Crossing/TM Center

Timeline

  1. Jan. 13, 2022

    Application Complete: Done

    Task closed by script.

  2. Jan. 13, 2022

    GIS Final Review: No Comment

  3. June 8, 2021

    Public hearing: Meridian City Council

    Outcome: Approved.

  4. June 8, 2021

    Decision: Approved

    Meridian City Council: Approved.

  5. May 12, 2021

    Final Action: Application Complete

  6. May 11, 2021

    Public hearing: Meridian City Council

    Outcome: FF-CL Requested for Approval.

  7. May 11, 2021

    Decision: FF-CL Requested for Approval

    Meridian City Council: FF-CL Requested for Approval.

  8. April 27, 2021

    Public hearing: Meridian City Council

    Outcome: FF-CL Requested for Approval.

  9. April 27, 2021

    Decision: FF-CL Requested for Approval

    Meridian City Council: FF-CL Requested for Approval.

  10. April 15, 2021

    City Council Hearing: Approved

  11. April 13, 2021

    Public hearing: Meridian City Council

  12. March 19, 2021

    Planning and Zoning Hearing: Recommend Approval

  13. March 18, 2021

    Public hearing: Meridian Planning and Zoning Commission

    Outcome: Recommended Approval.

  14. March 18, 2021

    Recommended Approval

    Meridian Planning and Zoning Commission: Recommended Approval.

  15. Jan. 21, 2021

    Public hearing: Meridian Planning and Zoning Commission

  16. Dec. 4, 2020

    Application Complete: Done

  17. Dec. 4, 2020

    Planning and Zoning Hearing: Continued

  18. Dec. 3, 2020

    Public hearing: Meridian Planning and Zoning Commission

  19. Sept. 18, 2020

    Application Complete: Done

  20. Sept. 18, 2020

    Planning and Zoning Hearing: Continued

  21. Sept. 17, 2020

    Public hearing: Meridian Planning and Zoning Commission

  22. Aug. 10, 2020

    Application Complete: Done

  23. Aug. 10, 2020

    Community Development Review: Staff Recommend Approval w/ Cond

  24. Aug. 6, 2020

    Public hearing: Meridian Planning and Zoning Commission

  25. Aug. 3, 2020

    Application Complete: Done

  26. Aug. 3, 2020

    Parks Review: Review Complete w/ Cond

    uploaded

  27. July 6, 2020

    Application Complete: Done

  28. July 6, 2020

    MFD Plan Review: Review Complete w/ Cond

    Comments uploaded to Accela and emailed to the clerk.

  29. July 1, 2020

    Application Complete: Done

  30. July 1, 2020

    Reclaimed Water Review: Connection NOT required

    Connection not required.

  31. July 1, 2020

    MPD Review: Review Complete w/ Cond

    See police comments sent to clerks office Chris Johnson 7/1/20

  32. June 26, 2020

    Application Complete: Done

  33. June 26, 2020

    Water Modeling Review: Review Complete

    See both the water markup and Engineering-Water Staff Report Comments

  34. June 26, 2020

    Transportation Plan Review: Review Complete w/ Cond

    A street light plan will need to be included in the final plat application. Street light plan requirements are listed in section 6-7 of the City's Design Standards.

  35. June 25, 2020

    Application Complete: Done

  36. June 25, 2020

    Floodplain Review: FLDP Not Required

  37. June 25, 2020

    Wastewater Modeling Review: Review Complete

    See Engineering-WW Staff Report Comments

  38. June 25, 2020

    GIS Review: Review Complete

  39. June 25, 2020

    Transmit and Notice: Distribute for Plan Review

  40. June 25, 2020

    Plan Intake: Accepted

  41. June 18, 2020

    Application Complete: Done

  42. June 18, 2020

    Reclaimed Water Review: Connection NOT required

    Connection Not Required.

  43. June 17, 2020

    Application Complete: Done

  44. June 17, 2020

    Planning Cursory Review: Return to Plan Intake

  45. June 17, 2020

    GIS Cursory Review: Entered in GIS

  46. June 17, 2020

    Plan Intake: Application Submitted

  47. June 16, 2020

    Application Complete: Done

  48. June 16, 2020

    Plan Intake: Cursory Review

  49. June 16, 2020

    Application filed

Documents

Staff reports

Other documents

  • Email Confirmation Final Action Courtesy Letter

    May 21, 2021 · 151 KB · Viewable by All

  • Legal Description for RZ to C-G north

    March 12, 2021 · 1.0 MB · Viewable by All

  • Legal Description for RZ to C-G South

    March 12, 2021 · 1.8 MB · Viewable by All

  • Legal Description for RZ to R-40

    March 12, 2021 · 1.0 MB · Viewable by All

  • Pathways Comments

    Aug. 3, 2020 · 51 KB · Viewable by All

  • Engineering-Water Staff Report Comments_KK

    June 26, 2020 · 18 KB · Viewable by All

  • TM Center - Water Markup

    June 26, 2020 · 1.3 MB · Viewable by All

  • TM Center Sewer Comment

    June 25, 2020 · 1.3 MB · Viewable by All

  • Autocad file

    June 16, 2020 · 6.9 MB · Viewable by All

  • Elevations

    June 16, 2020 · 4.1 MB · Viewable by All

  • Geotech Report

    June 16, 2020 · 1.7 MB · Viewable by All

  • Landscape Plan

    June 16, 2020 · 3.0 MB · Viewable by All

  • Pathway Plan

    June 16, 2020 · 584 KB · Viewable by All

  • Phasing Plan

    June 16, 2020 · 259 KB · Viewable by All

  • Pre-plat

    June 16, 2020 · 5.5 MB · Viewable by All

The Boise Builds daily briefing

Every new planning application in Boise, Meridian, Nampa and Caldwell, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.