Planning project · Planning application
New 2,389-square-foot well head treatment system approved
The project would add a water treatment system for a well on a 0.38-acre site. City staff approved it administratively on Jan. 21, 2026, after the application was filed on March 13, 2025.

About this application
New well head treatment system
Project name on file: 7180 W BETHEL ST
Timeline
Two days ago
5 documents added
Jan. 23, 2026
Planning Applications: Project Entitled
Dec. 2, 2025
Pending Application Submittal: Planning Applications in Review
Updated Via Script
Nov. 20, 2025
Pending Application Submittal: Planning Applications in Review
Nov. 20, 2025
IDR Review Complete: IDR Waived
Nov. 20, 2025
Neighborhood Meeting Review: Not Required
April 10, 2025
Concept Review Complete: CR Complete - Type 3
March 31, 2025
Early Assistance Review: Send to Concept Review
March 20, 2025
Early Assistance Review: Corrections Required
Please provide a letter from the irrigation company that they will permit you to build on their easement.Please provide elevations
March 13, 2025
Application Submittal: Online
March 13, 2025
Application filed
Documents
Site plans
- Download PDS-Other Small Docs - SITE PLAN
March 13, 2025 · 1 page · 360 KB · PDS-Other Small Docs
Project narrative
- Download PDS-Concept Review Summary Report -
April 10, 2025 · 3 pages · 455 KB · PDS-Concept Review Summary Report
- Download PDS-Other Small Docs - PROJECT DESCRIPTION
March 13, 2025 · 1 page · 370 KB · PDS-Other Small Docs
Application
- Download PDS-Application
March 13, 2025 · 2 pages · 154 KB · PDS-Application
Other documents
- PDS-Other Small Docs - LICENSE AGREEMENT
March 31, 2025 · 625 KB · PDS-Other Small Docs