New 2,389-square-foot well head treatment system approved

The project would add a water treatment system for a well on a 0.38-acre site. City staff approved it administratively on Jan. 21, 2026, after the application was filed on March 13, 2025.

ApprovedPLN25-00231Filed March 13, 2025Liberty Park · 7180 W Bethel St+1 related filing
Site plan for New 2,389-square-foot well head treatment system approved
Site plan from the application documents.
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

New well head treatment system

Project name on file: 7180 W BETHEL ST

Timeline

  1. Two days ago

    5 documents added

  2. Jan. 23, 2026

    Planning Applications: Project Entitled

  3. Dec. 2, 2025

    Pending Application Submittal: Planning Applications in Review

    Updated Via Script

  4. Nov. 20, 2025

    Pending Application Submittal: Planning Applications in Review

  5. Nov. 20, 2025

    IDR Review Complete: IDR Waived

  6. Nov. 20, 2025

    Neighborhood Meeting Review: Not Required

  7. April 10, 2025

    Concept Review Complete: CR Complete - Type 3

  8. March 31, 2025

    Early Assistance Review: Send to Concept Review

  9. March 20, 2025

    Early Assistance Review: Corrections Required

    Please provide a letter from the irrigation company that they will permit you to build on their easement.Please provide elevations

  10. March 13, 2025

    Application Submittal: Online

  11. March 13, 2025

    Application filed

Documents

Site plans

Project narrative

Application

Other documents

  • PDS-Other Small Docs - LICENSE AGREEMENT

    March 31, 2025 · 625 KB · PDS-Other Small Docs

Nearby

The Boise Builds daily briefing

Every new planning application in Boise, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.