Idaho Power seeks about 8% expansion of electrical substation

The utility wants to enlarge the fenced yard of the Eckert Substation for new and upgraded equipment, add a driveway and fully enclose the new area. City staff are reviewing the request administratively.

In reviewPLN26-00524Filed May 29, 2026Barber Valley · 4501 E Warm Springs Ave+2 related filings
Site plan for Idaho Power seeks about 8% expansion of electrical substation
Site plan from the application documents.
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

Expansion to Eckert Substation

Project name on file: 4501 E WARM SPRINGS AVE - CUP minor Mod & DRH minor

Timeline

  1. Sept. 14, 2026

    Pending Application Submittal: Planning Applications in Review

  2. July 7, 2026

    Concept Review Complete: CR Complete - Type 2

  3. May 29, 2026

    Application Submittal: Online

  4. May 29, 2026

    Application filed

Documents

Site plans

  • Draft site plan for the Eckert Substation expansion, a one-page sheet dated 5.29.2026.

    May 29, 2026 · 1 page · 145 KB · PDS-Other Small Docs

    Download Draft site plan

Project narrative

Application

Other documents

  • PDS-Other Small Docs - PRIOR CUP APPROVAL FOR THE ECKERT SUBSTATION AND AN ASSOCIATED TRANSMISSION LINE.

    May 29, 2026 · 309 KB · PDS-Other Small Docs