Development review · Planning application
Office site landscaping update with new van-accessible parking approved
The approved plan redoes front landscaping on a 0.15-acre office site with water-tolerant plants, trees and rock, plus an underground sprinkler system. It also adds new van-accessible parking spaces. The city lists the file as finaled.
About this application
Narrative being uploaded. Updates to front exterior landscaping, including new van accessible parking spaces, installation of new water-tolerant plant material, trees, and rock. Automatic underground sprinkler system will insure complete and separate irrigation of hydrozones.
Project name on file: Studio H Office Site Modfication
Timeline
Jan. 27, 2026
MFD Plan Review: Approved
Jan. 27, 2026
Planning Review: Approved
Jan. 22, 2026
ACHD Review: Approved
Jan. 16, 2026
Planning Review: More Information Required
Jan. 13, 2026
MFD Plan Review: More Information Required
Jan. 12, 2026
Wastewater Modeling Review: Approved
Jan. 12, 2026
Transportation Plan Review: No Comment
Jan. 9, 2026
MPD Review: No Comment
Jan. 6, 2026
Water Modeling Review: Approved
Jan. 5, 2026
GIS Review: Approved
Jan. 5, 2026
Land Development Review: Approved
Dec. 4, 2025
Planning Review: More Information Required
Nov. 26, 2025
Floodplain Review: FLDP Not Required
Nov. 26, 2025
Application Submittal: More Information Required
HiPlease upload the following PDF files.ElevationsSite planRecorded platThank you!
Nov. 26, 2025
Application Submittal: Accepted
Nov. 26, 2025
Application filed