Conditional use · Planning application

52,000-square-foot church with 320 parking spaces approved in two phases

Meridian approved a conditional use permit for Poiema Calvary Chapel to build a church in two phases on about 7 acres. The Jan. 7, 2021, decision covers the full build-out and 320 parking spaces.

ApprovedH-2020-0095Filed Sept. 24, 2020Southeast Meridian · 3727 Lake Hazel+8 related filings
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

Conditional Use Permit request to construct a new church facility built in two phases to total 52,000 square feet at total build-out and 320 parking spaces on Lot 1, Block 2, approximately 7 acres, of Poiema Subdivision, zoned R-15.

Project name on file: Poiema Calvary Chapel

Timeline

  1. Jan. 8, 2021

    Application Complete: Done

  2. Jan. 8, 2021

    Final Action: Application Complete

    Findings signed on 1-7

  3. Jan. 7, 2021

    Public hearing: Meridian Planning and Zoning Commission

    Outcome: Approved.

  4. Jan. 7, 2021

    Decision: Approved

    Meridian Planning and Zoning Commission: Approved.

  5. Dec. 18, 2020

    Application Complete: Done

  6. Dec. 18, 2020

    Planning and Zoning Hearing: Approved

  7. Dec. 17, 2020

    Public hearing: Meridian Planning and Zoning Commission

  8. Nov. 20, 2020

    Application Complete: Done

  9. Nov. 20, 2020

    Planning and Zoning Hearing: Continued

  10. Nov. 19, 2020

    Public hearing: Meridian Planning and Zoning Commission

  11. Nov. 16, 2020

    Application Complete: Done

  12. Nov. 16, 2020

    Community Development Review: Staff Recommend Approval w/ Cond

  13. Oct. 30, 2020

    Application Complete: Done

  14. Oct. 30, 2020

    Parks Review: Review Complete

    No Pathways MP Interface -- Ten Mile Pathway is located on opposite side of Creek from church.

  15. Oct. 26, 2020

    Application Complete: Done

  16. Oct. 26, 2020

    Floodplain Review: FLDP Required

    Required Hydraulic and Hydrologic study complete. Study indicates large portion of site is in the 1% floodplain. Culvert needs to be replaced as designed to remove area from floodplain. Floodplain Development Permit required. Requirements dependent on if culvert is replaced as designed.

  17. Oct. 23, 2020

    Application Complete: Done

  18. Oct. 23, 2020

    MFD Plan Review: Review Complete w/ Cond

  19. Oct. 12, 2020

    Application Complete: Done

  20. Oct. 12, 2020

    Water Modeling Review: Review Complete

    See Engineering-Water Staff Report Comments

  21. Oct. 9, 2020

    Application Complete: Done

  22. Oct. 9, 2020

    Wastewater Modeling Review: Review Complete

    See Engineering-WW Staff Report Comments

  23. Oct. 9, 2020

    Transportation Plan Review: Review Complete w/ Cond

    A street light plan will need to be included in the final plat and/or building permit application. Street light plan requirements are listed in section 6-7 of the City's Design Standards. A future installation agreement for streetlight will be required for the streetlights on E. Lake Hazel Road due to an upcoming ACHD project

  24. Oct. 8, 2020

    Application Complete: Done

  25. Oct. 8, 2020

    MPD Review: No Comment

  26. Oct. 8, 2020

    GIS Review: Review Complete

  27. Oct. 7, 2020

    Application Complete: Done

  28. Oct. 7, 2020

    Reclaimed Water Review: Connection NOT required

  29. Oct. 7, 2020

    Floodplain Review: Manual Review Required

  30. Oct. 7, 2020

    Transmit and Notice: Distribute for Plan Review

  31. Oct. 7, 2020

    Legal Description Review: Verified Legal Description

  32. Oct. 7, 2020

    Planning Cursory Review: Return to Plan Intake

  33. Oct. 7, 2020

    GIS Cursory Review: No Comment

  34. Oct. 7, 2020

    Plan Intake: Cursory Review

  35. Oct. 7, 2020

    Plan Intake: Accepted

  36. Sept. 24, 2020

    Application Complete: Done

  37. Sept. 24, 2020

    Plan Intake: Application Submitted

  38. Sept. 24, 2020

    Application filed

Documents

Site plans

Other documents

  • Email Confirmation Final Action Courtesy Letter

    Jan. 28, 2021 · 1.0 MB · Viewable by All

  • Engineering-Water Staff Report Comments_KK

    Oct. 12, 2020 · 18 KB · Viewable by All

  • Engineering-WW Staff Report Comments_TG

    Oct. 9, 2020 · 13 KB · Viewable by All

  • Application Materials

    Oct. 7, 2020 · 30.8 MB · Viewable by All