Planning project · Planning application
Accessory dwelling unit on hillside lot proposed, needs hillside review
The application seeks an accessory dwelling unit on a 0.62-acre residential lot, along with a hillside development review. It was filed Oct. 24 and is pending submittal, with city staff set to decide administratively.
About this application
ADU & CAT II Hillside
Project name on file: 2710 E TABLE ROCK RD
Timeline
Nov. 18, 2025
Concept Review Complete: CR Complete - Type 2
Nov. 5, 2025
Concept Review Complete: Corrections Required
- Site plan shows building within the Building Envelope EasementPlease provide me with an updated Site Plan that reflects the ADU outside of this easement
Oct. 24, 2025
Concept Review Complete: Engineering Preview
Oct. 24, 2025
Concept Review Complete: Engineering Preview Complete
A determination has been made that this project will be a Category II Hillside project due to the nature of surrounding slopes. In addition to the already submitted documents, additional documents may be required during the CFH Review process.Additional documents that you can expect to provide will be a geotechnical report with a possibility of a global slope stability analysis; structural calculations for any retaining wall that is greater than four feet of height, more than one retaining wall when the horizontal interior distance between the retaining walls is less than 10 feet and the total of all retaining walls exceeds four feet in height, a retaining wall having a surcharge, or having a backslope greater than three feet horizontal to one foot vertical; and civil plans.NOTE: The hazards of developing and building on property, especially in the Boise foothills, is well known. It is the responsibility of the applicant/owner’s design, geological, and engineering professionals, not the City, to identify, address, and mitigate any hazards to the site. Satisfying these Conditions of Approval is for limited [City purpose] only and should not be relied on for design, geological or engineering purposes.If you would like to discuss this determination, please contact us at HillsideDrainage@cityofboise.org or we can set up a meeting if you prefer.
Oct. 24, 2025
Application Submittal: Online
Oct. 24, 2025
Application filed
Documents
Other documents
- PDS-Concept Review Summary Report -
Nov. 18, 2025 · 464 KB · PDS-Concept Review Summary Report
- PDS-Application
Oct. 24, 2025 · 158 KB · PDS-Application
- PDS-Other Small Docs - ADDITIONAL INFORMATION
Oct. 24, 2025 · 692 KB · PDS-Other Small Docs
- PDS-Other Small Docs - PROJECT DESCRIPTION
Oct. 24, 2025 · 484 KB · PDS-Other Small Docs
- PDS-Other Small Docs - SITE PLAN
Oct. 24, 2025 · 1.9 MB · PDS-Other Small Docs