Planning project · Planning application

252-unit multifamily project approved on 11.65-acre commercial site

The Design Review Commission approved the apartment project, which totals about 320,000 square feet of building space. A public hearing was held June 18, and the decision came Sept. 11.

ApprovedPLN26-00239Filed March 9, 2026Northwest · 9474 W State St+4 related filings
Site plan for 252-unit multifamily project approved on 11.65-acre commercial site
Site plan from the application documents.
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

Multi-family Residential

Project name on file: 9474 W STATE ST

Timeline

  1. Yesterday

    7 documents added

  2. Sept. 16, 2026

    Planning Applications: Additional CR Needed

  3. Sept. 16, 2026

    Concept Review Complete: Generate AWS

    Hi! These folks want to now change their AWS applicant to be Stephanie. This is for PLN26-00239I’ve updated the contact info in the PLN. Can you please help with generating another AWS application?Thank you, Katelyn Menuge, AICPSenior Planner, Design ReviewPlanning and Development ServicesOffice: 208-608-7081kmenuge@cityofboise.org

  4. June 22, 2026

    Pending Application Submittal: Planning Applications in Review

  5. June 18, 2026

    Public hearing: Hybrid

  6. June 18, 2026

    IDR Review Complete: IDR Complete

  7. June 18, 2026

    Neighborhood Meeting Review: Completed

  8. May 28, 2026

    Concept Review Complete: Generate AWS

    Reopened Concept Review task to generate new AWS app per K. Menuge

  9. May 12, 2026

    Concept Review Complete: CR Complete - Type 2

    Sent back to Concept Review to regenerate NBR due to Primary Contact change.

  10. May 12, 2026

    Concept Review Complete: CR Complete - Type 3

    Resubmitting Concept Review as Type 3 to generate new NBR due to Primary Contact Change.

  11. March 31, 2026

    Concept Review Complete: Generate AWS

  12. March 31, 2026

    Concept Review Complete: CR Complete - Type 3

  13. March 26, 2026

    Public hearing: Hybrid

  14. March 9, 2026

    Application Submittal: Online

  15. March 9, 2026

    Application filed

Documents

Plans

  • Cover letter from Sweetwater Companies' consultant describing the Westlock Village multi-family design review, access points, and six 3-story buildings totaling 252 units.

    June 5, 2026 · 16 pages · 29.5 MB · PDS-Other Small Docs

    Download Integrated design review (IDR) information letter

Other documents

  • PDS-Interdepartmental Review Summary Report - 6/18/2026

    June 26, 2026 · 1.0 MB · PDS-Interdepartmental Review Summary Report

  • PDS-Other Small Docs - UPDATED BUILDING ELEVATIONS FOR IDR 6/18/2026

    June 18, 2026 · 5.5 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - CONCEPT REVIEW SUMMARY 3/26/2026

    March 31, 2026 · 751 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - CONCEPT REVIEW SUMMARY 3/26/2026

    March 31, 2026 · 726 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - IDR MATERIALS_3/26/2026

    March 12, 2026 · 5.7 MB · PDS-Other Small Docs

  • PDS-Application

    March 9, 2026 · 158 KB · PDS-Application

Nearby

The Boise Builds daily briefing

Every new planning application in Boise, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.