Planning project · Planning application
New single-family home proposed on hillside lot, with extra slope review required
The plan calls for one single-family home with an attached garage on a 0.24-acre lot. The city says it needs the stricter hillside review because of steep slopes and unstable soils, and the application is under administrative review.

About this application
No description has been published for this record yet.
Project name on file: 3615 E ASTEROID CT
Timeline
June 29, 2026
Pending Application Submittal: Planning Applications in Review
April 16, 2026
Concept Review Complete: CR Complete - Type 2
April 15, 2026
Concept Review Complete: Engineering Preview
April 15, 2026
Concept Review Complete: Engineering Preview Complete
A determination has been made that this project will be a Category II Hillside project due to slope, erosion-prone soils, unstable soils, earth movement, and other geologic and hydrologic hazards. In addition to the already submitted documents, additional documents may be required during the CFH Review process.Additional documents that you can expect to provide will be a site-specific geotechnical report with the possibility of a global slope stability analysis (please see the Agency Comment for Hillside Retaining Wall Permitting within this PLN); structural calculations for any retaining wall system that is greater than four feet in height from top of foundation to top of wall, that has more than one wall when the interior horizontal distance between the walls is less than 10 feet and the total height of all walls exceeds four feet, that has a surcharge, that has a backslope greater than three feet horizontal to one foot vertical, or that has structural components (these requirements will be assessed again at the time of occupancy); and civil plans.A subgrade inspection by a geotechnical firm will be required at the time of construction once the subgrade is exposed and prior to placement of foundation materials or forms/rebar. A report of the inspection will need to be submitted and accepted by PW Hillside (HillsideDrainage@cityofboise.org) before scheduling your inspection with the Building Department and receiving final occupancy.NOTE: The hazards of developing and building on a property, especially in the Boise foothills, are well known. It is the responsibility of the applicant/owner’s design, geological, and engineering professionals, not the City, to identify, address, and mitigate any hazards to the site. Satisfying these Conditions of Approval is for limited [City purpose] only and should not be relied on for design, geological or engineering purposes. Developer will comply with all requirements of Boise City Hillside Development Code Sections or submit evidence satisfactory to the Boise City Engineer that the proposed development is exempt from the requirements therein stated due to location, topography and/or the absence of adverse conditions associated with slope stability, ground water, erosion and sedimentation.If you would like to discuss this determination, please contact us at HillsideDrainage@cityofboise.org or we can set up a meeting if you prefer.
April 15, 2026
Application Submittal: Online
April 15, 2026
Application filed
Documents
Site plans
- Download Site plan with general notes and building area totals
Site plan sheet with general construction notes, a building area breakdown totaling 3,580 square feet, and designer contact information from Biltmore Company.
April 15, 2026 · 1 page · 758 KB · PDS-Other Small Docs
Project narrative
- Download PDS-Concept Review Summary Report -
April 16, 2026 · 3 pages · 467 KB · PDS-Concept Review Summary Report
Application
- Download Planning project application form
Application for a single-family dwelling on an A-1 zoned lot, noting a Hillside Questionnaire is required and certifying the applicant's authority to file.
April 15, 2026 · 2 pages · 158 KB · PDS-Application
- Download PDS-Other Small Docs - BP.L31.B10 PW HILLSIDE QUESTIONNAIRE
April 15, 2026 · 1 page · 677 KB · PDS-Other Small Docs
Correspondence
- Download PDS-Agency Comments - HILLSIDE RETAINING WALL PERMITTING_OCTOBER2025
April 15, 2026 · 5 pages · 804 KB · PDS-Agency Comments