Hillside development application approved for 1.31-acre lot

City staff approved a hillside application on a 1.31-acre site on June 12. Plans on file include grading, retaining walls, erosion control and a storage and mechanical crawlspace or basement. The filing does not say what will be built.

ApprovedPLN26-00290Filed March 25, 2026Boise Heights · 363 N Panorama Pl+3 related filings
Site plan for Hillside development application approved for 1.31-acre lot
Site plan from the application documents.
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

About this application

Hillside application

Project name on file: 363 N PANORAMA PL

Timeline

  1. June 12, 2026

    Planning Applications: Project Entitled

  2. April 3, 2026

    Pending Application Submittal: Planning Applications in Review

  3. April 3, 2026

    Concept Review Complete: CR Complete - Type 2

  4. April 2, 2026

    Concept Review Complete: Engineering Preview Complete

    A determination has been made that this project will be a Category II Hillside project due to slope, erosion-prone soils, unstable soils, earth movement, and other geologic and hydrologic hazards. In addition to the already submitted documents, additional documents may be required during the CFH Review process.Additional documents that you can expect to provide will be a site-specific geotechnical report with the possibility of a global slope stability analysis (please see the Agency Comment for Hillside Retaining Wall Permitting within this PLN); and structural calculations for any retaining wall that is greater than four feet of height, more than one retaining wall when the horizontal interior distance between the retaining walls is less than 10 feet and the total of all retaining walls exceeds four feet in height, a retaining wall having a surcharge, having a backslope greater than three feet horizontal to one foot vertical, or that has structural components (these requirements will be assessed again at the time of occupancy).A subgrade inspection by a geotechnical firm will be required at the time of construction once the subgrade is exposed and prior to placement of foundation materials or forms/rebar. A report of the inspection will need to be submitted and accepted by PW Hillside (HillsideDrainage@cityofboise.org) before scheduling your inspection with the Building Department and receiving final occupancy.NOTE: The hazards of developing and building on a property, especially in the Boise foothills, are well known. It is the responsibility of the applicant/owner’s design, geological, and engineering professionals, not the City, to identify, address, and mitigate any hazards to the site. Satisfying these Conditions of Approval is for limited [City purpose] only and should not be relied on for design, geological or engineering purposes. Developer will comply with all requirements of Boise City Hillside Development Code Sections or submit evidence satisfactory to the Boise City Engineer that the proposed development is exempt from the requirements therein stated due to location, topography and/or the absence of adverse conditions associated with slope stability, ground water, erosion and sedimentation.If you would like to discuss this determination, please contact us at HillsideDrainage@cityofboise.org or we can set up a meeting if you prefer.

  5. April 1, 2026

    Concept Review Complete: Engineering Preview

  6. March 25, 2026

    Application Submittal: Online

  7. March 25, 2026

    Application filed

Documents

Site plans

Plans

Other documents

  • PDS-Concept Review Summary Report -

    April 3, 2026 · 462 KB · PDS-Concept Review Summary Report

  • PDS-Other Small Docs - HILLSIDE RETAINING WALL PERMITTING_OCTOBER2025

    April 2, 2026 · 804 KB · PDS-Other Small Docs

  • PDS-Application

    March 25, 2026 · 158 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - BUILDING ELEVATIONS WITH MATERIALS

    March 25, 2026 · 1.5 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - BUILDING ELEVATIONS WITH MATERIALS

    March 25, 2026 · 1.7 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - BUILDING ELEVATIONS WITH MATERIALS

    March 25, 2026 · 1.6 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - COMPLETED HILLSIDE CHECKLIST

    March 25, 2026 · 801 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - COMPLETED HILLSIDE QUESTIONNAIRE

    March 25, 2026 · 672 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - DETAILED LETTER OF EXPLANATION FOR THE PROJECT INTENT

    March 25, 2026 · 80 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - ESC REPORT SIGNED BY CIVIL ENGINEER

    March 25, 2026 · 3.7 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - EXISTING SITE PHOTOS SHOWING EXISTING PROPERTY CONDITIONS

    March 25, 2026 · 10.1 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - FLOOR PLAN OF PROPOSED MAIN FLOOR

    March 25, 2026 · 1.4 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - FLOOR PLAN OF PROPOSED UPPER FLOOR

    March 25, 2026 · 3.5 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - GEOTECH REPORT

    March 25, 2026 · 2.9 MB · PDS-Other Small Docs

  • PDS-Other Small Docs - STATEMENT OF LEGAL INTEREST SIGNED BY OWNER

    March 25, 2026 · 272 KB · PDS-Other Small Docs

  • PDS-Other Small Docs - VEOLIA FIRE FLOW REPORT

    March 25, 2026 · 111 KB · PDS-Other Small Docs

Nearby

The Boise Builds daily briefing

Every new planning application in Boise, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.