Master site plan (time extension) · Planning application
Approved extension for 12-apartment building plan in Ada County
County commissioners approved a two-year extension, to Aug. 10, 2027, of an earlier approval for one 15,000-square-foot apartment building on a 0.66-acre site. The applicant cited rising construction costs, labor shortages and tighter lending.
From the filing
The application's description as it appears in Ada County's record. See the official record
The applicant is asking Ada County's Board of County Commissioners for a two-year extension of an approved master site plan for a 12-apartment building at 6162 S. Maple Grove Road. The apartment building is about 15,000 square feet, and the applicant says the extension is needed because of rising construction costs, labor shortages, and tighter lending, and that the project is being sold to another developer. Staff recommends approval, and the document does not record a Board decision.
Board-Level Time Extension for a Master Site Plan for a 12-unit multi-family deveopment. The property is located at 6162 S Maple Grove Rd; Section 36, T.3N, R.1E.
Timeline
Aug. 13, 2025
Ada County staff recommended approval
Aug. 13, 2025
Approved
Ada County Board of County Commissioners: Approved.
Aug. 13, 2025
Public hearing: Ada County Board of County Commissioners
Aug. 8, 2025
Document added: Memo (Board of County Commissioners, Aug 13, 2025)
Aug. 6, 2025
Document added: Staff report (Board of County Commissioners, Aug 13, 2025)
Aug. 6, 2025
Document added: Findings (Board of County Commissioners, Aug 13, 2025)
July 1, 2025
Application filed
Documents
Staff reports
- Download Staff memo adding exhibit 21, owner email on property sale
Ada County staff memo to commissioners adding Exhibit 21, an August 4, 2025 owner email saying the property is pending sale and the buyer plans to break ground soon.
Aug. 8, 2025 · 3 pages · 621 KB · Staff Memo
- Download Staff report for Board of County Commissioners hearing
Staff report to the Ada County Board of Commissioners recommending on a two-year board-level time extension for a master site plan for a 12-unit multi-family development.
Aug. 6, 2025 · 36 pages · 14.9 MB · Staff Report
Decisions
- Download Findings of fact, conclusions of law and order
Board of County Commissioners findings for a time extension on a master site plan for a 12-unit multi-family project, following the Aug. 13, 2025 public hearing.
Aug. 6, 2025 · 6 pages · 240 KB · Findings