Conditional use · Planning application

Idaho Power substation approved by county planning commission

The substation would occupy about 5 acres, start with one transformer with room for up to three, and reach 120 megawatts at full build-out. Construction is expected to begin in 2029, subject to conditions on dust, noise, drainage and screening.

Approved202502304Filed Nov. 21, 2025Blacks Creek
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

From the filing

The application's description as it appears in Ada County's record. See the official record

Idaho Power Company has applied for a conditional use permit and master site plan to build the Eisenman Electrical Distribution Substation on an 8.36-acre property off S Eisenman Road in southeast Ada County, southeast of the Boise Airport. The substation would occupy about 5 acres, start with one transformer with room for up to three, and provide up to 120 megawatts at full build-out. Staff recommends approval, and construction is anticipated to begin in 2029.

An application for the approval of a Conditional Use and Master Site Plan for an Idaho Power Electrical Distribution Substation. The property is located at TBD S Eisenman Rd (S1514120025) and contains approximately 8.36 acres in the M3 District; Section: 14, Town: 2N, Range: 2E.

Timeline

  1. March 12, 2026

    Ada County Planning and Zoning Commission voted to approve (5-0)

    Commission action: Approved; (5-0)

  2. March 12, 2026

    Ada County staff recommended approval

  3. March 12, 2026

    Approved

    Ada County Planning and Zoning Commission: Approved.

  4. March 12, 2026

    Public hearing: Ada County Planning and Zoning Commission

  5. March 4, 2026

    Document added: Staff report (Planning and Zoning Commission, Mar 12, 2026)

  6. March 4, 2026

    Document added: Findings (Planning and Zoning Commission, Mar 12, 2026)

  7. Nov. 21, 2025

    Application filed

Documents

Staff reports

  • Planning staff report on Idaho Power's application for a 138-kilovolt electrical distribution substation on an 8.36-acre split-zoned site, with the hearing set for March 12, 2026.

    March 4, 2026 · 144 pages · 24.1 MB · Staff Report

    Download Staff report for conditional use and master site plan

Decisions

  • Planning and Zoning Commission findings for Idaho Power's electrical distribution substation conditional use application, covering procedural history, notice, and project description.

    March 4, 2026 · 23 pages · 387 KB · Findings

    Download Findings of fact, conclusions of law and order