0.81-mile underground natural gas pipeline approved with conditions

Northwest Pipeline LLC's 10-inch line would connect to an existing pipeline, with a fenced tap site and small corrosion-protection posts above ground. The county commission approved it Sept. 10, requiring an Idaho Power crossing agreement and on-site drainage.

Approved202601149Filed June 29, 2026Ten Mile Creek · S Cole Rd+3 related filings
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

From the filing

The application's description as it appears in Ada County's record. See the official record

Northwest Pipeline LLC proposes a roughly 0.81-mile, 10-inch underground natural gas pipeline on state-owned land near S. Pleasant Valley Road south of Kuna. It would connect to an existing pipeline and include a tap site, an access road, fencing, and corrosion-protection equipment. The Ada County Planning and Zoning Commission approved it with conditions.

An application for approval of a conditional use and master site plan for a public-quasi public use for an approximately 0.81-mile long, 10-inch diameter, natural gas lateral pipeline connecting with an existing pipeline. Also included are tap site appurtenances and cathodic protection facilities. The project is located at 14195 S. Pleasant Valley Road and contains approximately 863.64 acres within the Rural Preservation (RP) District; Section 29, T.2N., 2E.; Section 30, T.2N, R.2E.; and Section 31, T.2N., R.2E.

Timeline

  1. Sept. 10, 2026

    Ada County Planning and Zoning Commission voted to approve (6-0)

    Commission action: Approved (6-0)

  2. Sept. 10, 2026

    Ada County staff recommended approval

  3. Sept. 10, 2026

    Approved

    Ada County Planning and Zoning Commission: Approved.

  4. Sept. 10, 2026

    Public hearing: Ada County Planning and Zoning Commission

  5. Sept. 2, 2026

    Document added: Staff report (Planning and Zoning Commission, Sep 10, 2026)

  6. Sept. 2, 2026

    Document added: Findings (Planning and Zoning Commission, Sep 10, 2026)

  7. June 29, 2026

    Application filed

Documents

Staff reports

  • Staff analysis of a 0.81-mile underground natural gas lateral pipeline in the Rural Preservation district, covering compatibility with the comprehensive plan and conditions of approval.

    Sept. 2, 2026 · 125 pages · 17.8 MB · Staff Report

    Download Staff report for conditional use and master site plan

Decisions

  • Planning and Zoning Commission findings for a conditional use application by Northwest Pipeline LLC to build a 0.81-mile underground natural gas lateral pipeline, with the record and procedural notice steps.

    Sept. 2, 2026 · 13 pages · 316 KB · Findings

    Download Findings of fact, conclusions of law and order