County approves 150-megawatt solar farm with battery storage and substation

Developer DESRI's project includes about 354,000 solar panels, battery storage and a mostly underground transmission line. Commissioners approved it Dec. 30, along with a variance to exceed the 5% lot coverage limit, and conditions include a raptor nest survey before construction.

Approved202501571Filed Aug. 12, 2025Blacks Creek · S Pleasant Valley Rd+1 related filing
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

From the filing

The application's description as it appears in Ada County's record. See the official record

DESRI proposes a solar power facility with battery storage, an on-site substation, and a transmission line on about 1,376 acres of mostly state-owned and private land near Kuna-Mora Road and S Pleasant Valley Road, roughly 10 miles east of Kuna. The project includes ground-mounted solar panel arrays, battery storage structures no taller than 15 feet, and a 5,000-square-foot maintenance building. The request also includes a variance to exceed the 5% lot coverage limit in the Rural Preservation zone.

Conditional Use and Master Site Plan for a Centralized Power Facility (Solar Farm), Electric Transmission Line, Battery Energy Storage System and Substation. Also included is a Variance to maximum site coverage. The property is generally located north of Kuna Mora Rd and east of S Cole Rd and contains approximately 2,600 acres in the Rural Preservation (RP) District; Sections 27, 28, 29, 30, 31, 32, 33, 34, 35, T.2N, R.2E and Section 3, T.1N, R.2E.

Timeline

  1. Dec. 30, 2025

    Approved

    Ada County Board of County Commissioners: Approved.

  2. Dec. 30, 2025

    Public hearing: Ada County Board of County Commissioners

  3. Dec. 10, 2025

    Ada County staff recommended approval

  4. Dec. 10, 2025

    Public hearing: Ada County Board of County Commissioners

  5. Dec. 5, 2025

    Document added: Memo (Board of County Commissioners, Dec 10, 2025)

  6. Dec. 3, 2025

    Document added: Staff report (Board of County Commissioners, Dec 10, 2025)

  7. Dec. 3, 2025

    Document added: Findings (Board of County Commissioners, Dec 10, 2025)

  8. Aug. 12, 2025

    Application filed

Documents

Staff reports

  • Planner's memo to the Board of County Commissioners listing public comments received Dec. 4, 2025, submitted after the staff report was published, including opposition emails.

    Dec. 5, 2025 · 5 pages · 345 KB · Staff Memo

    Download Staff memo with additional exhibits for Dec. 10 Board hearing
  • Staff report for the Dec. 10, 2025 Board hearing on DESRI's conditional use and master site plan for a 150 MW solar farm, transmission line, battery storage and substation, plus a site coverage variance.

    Dec. 3, 2025 · 1098 pages · 103.3 MB · Staff Report

    Download Staff report for Board of County Commissioners hearing

Decisions

The Boise Builds daily briefing

Every new planning application in the Treasure Valley, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.