Master site plan (time extension) · Planning application
Owners of Stone Crossing Event Center win more time to finish road work
Ada County commissioners approved a time extension for the event center's master site plan, giving the owner more time to finish Ada County Highway District road improvements and a new parking lot. A larger new event building would need a separate future land use application and public hearing, and it has not yet been…
From the filing
The application's description as it appears in Ada County's record. See the official record
Stone Crossing Event Center, at 9600 W. Brookside Lane in unincorporated Ada County near Boise, asks for more time to finish approved work tied to its event center permits. The owner needs the extra time to complete required Ada County Highway District road improvements and a new parking lot. The site is about 10 acres, and the event center was previously approved to hold up to 550 people.
Board-Level Time Extension for the Conditional Use, Master Site Plan, and Hillside application for the Stone Crossing Event Center. The property is located at 9600 W. Brookside Lane and contains approximately 10.0 acres in the Rural Residential (RR) District; Section 26, T.5N, R.1E. (x_ref: 202301034-HD).
Project name on file: Stone Crossing Event Center
Timeline
April 9, 2025
Ada County staff recommended approval
April 9, 2025
Approved
Ada County Board of County Commissioners: Approved.
April 9, 2025
Public hearing: Ada County Board of County Commissioners
April 4, 2025
Document added: Memo (Board of County Commissioners, Apr 9, 2025)
April 2, 2025
Document added: Staff report (Board of County Commissioners, Apr 9, 2025)
April 2, 2025
Document added: Findings (Board of County Commissioners, Apr 9, 2025)
March 4, 2025
Application filed
Documents
Staff reports
- Download Staff memo on additional exhibits for time extension
Ada County staff memo transmitting two late-submitted exhibits, including a March 31, 2025 opposition email from a resident, for the master site plan time extension.
April 4, 2025 · 10 pages · 468 KB · Staff Memo
- Download Staff report for time extension of master site plan
Staff report to the Board of County Commissioners recommending on a two-year time extension for the Stone Crossing Event Center conditional use, master site plan, and hillside application.
April 2, 2025 · 39 pages · 7.9 MB · Staff Report
Decisions
- Download Findings of fact, conclusions of law and order on time extension
Board of County Commissioners findings and order from the April 9, 2025 hearing on the master site plan time extension, covering procedural history, notice and the project description.
April 2, 2025 · 6 pages · 262 KB · Findings