Porch and patio addition proposed for single-family home on hillside lot

The plan is now reduced to a deck with no new walls. City planners say it needs hillside review because of steep slopes and unstable soils, and a geotechnical report is on file. Staff will review it administratively.

SubmittedPLN25-00390Filed May 7, 2025Highlands · 727 E Highland View Dr+1 related filing
Site plan for Porch and patio addition proposed for single-family home on hillside lot
Site plan from the application documents.
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

From the filing

The application's description as it appears in City of Boise's record. See the official record

Porch/patio addition to a single-family home in the Hillside Overlay.

Project name on file: 727 E HIGHLAND VIEW DR

Timeline

  1. Oct. 13, 2026

    12 documents added

  2. June 2, 2026

    Concept Review Complete: CR Complete - Type 2

  3. May 19, 2026

    Concept Review Complete: Engineering Preview Complete

    Based on submitted documents and limited overview of the property, a determination has been made that this project will be a Category II Hillside project due to slope, erosion-prone soils, unstable soils, earth movement, and other geologic and hydrologic hazards. In addition to the already submitted documents, additional documents may be required during the CFH Review process.Additional documents that you can expect to provide will be a site-specific geotechnical report with the possibility of a global slope stability analysis (please see the Agency Comment for Hillside Retaining Wall Permitting within this PLN); structural calculations for any retaining wall system that is greater than four feet in height from top of foundation to top of wall, that has more than one wall when the interior horizontal distance between the walls is less than 10 feet and the total height of all walls exceeds four feet, that has a surcharge, that has a backslope greater than three feet horizontal to one foot vertical, or that has structural components (these requirements will be assessed again at the time of occupancy); and civil plans. Please refer to the Hillside Development Requirements for Technical Reports for grading & drainage plan and geotechnical report requirements.A subgrade inspection by a geotechnical firm will be required at the time of construction once the subgrade is exposed and prior to placement of foundation materials or forms/rebar. A report of the inspection will need to be submitted and accepted by PW Hillside (HillsideDrainage@cityofboise.org) before scheduling your inspection with the Building Department and receiving final occupancy.

  4. May 18, 2026

    Pending Application Submittal: Start Additional IDR

  5. May 18, 2026

    Concept Review Complete: Notes

    Reset WF to Concept Review per K. Oneida.

  6. May 18, 2026

    Concept Review Complete: Engineering Preview

    Applicant has changed scope of work to see what category they will be

  7. June 23, 2025

    Concept Review Complete: CR Complete - Type 2

  8. June 17, 2025

    Concept Review Complete: Engineering Preview Complete

    A determination has been made that this project will be a Category II Hillside project due to the heights of the proposed retaining walls. In addition to the already submitted documents, additional documents may be required during the CFH Review process.Additional documents that you can expect to provide will be a structural calculations of any new retaining walls exceeding four feet in height, supporting slopes steeper than a 3H to 1V or having a surcharge; possibly an engineering review of any existing retaining walls; and civil plans showing existing and proposed drainage and grading aspects.If you would like to discuss this determination, please contact us at HillsideDrainage@cityofboise.org or we can set up a meeting if you prefer.

  9. June 13, 2025

    Concept Review Complete: Engineering Preview

  10. June 9, 2025

    Concept Review Complete: Corrections Required

    Please provide simple civil drawings showing the new contours created by the proposed work, elevations of top and bottom of the retaining walls and location of the retaining wall drain outfalls; details of the retaining wall showing dimensions, type and recommendations from the geotechnical report; structural calculations for any retaining wall that is greater than four feet of height; more than one retaining wall when the horizontal distance between the retaining walls is less than 10 feet and the total of all retaining walls exceeds four feet in height; a retaining wall having a surcharge; or having a backslope greater than three feet horizontal to one foot vertical.

  11. June 6, 2025

    Concept Review Complete: Engineering Preview

  12. May 23, 2025

    Concept Review Complete: Notes

    Emailed reminder for applicant to upload new site plan for Hillside screening.

  13. May 8, 2025

    Concept Review Complete: Corrections Required

    The provided Site plan is illegible. Please provide a Site plan that shows the proposed work (deck & walls, etc), shows the setbacks for the property and the type and height of the retaining wall(s); if other plans exist for the proposed work they can be provided as well. These can be hand-drawn on a legible drawing.

  14. May 7, 2025

    Concept Review Complete: Engineering Preview

  15. May 7, 2025

    Application Submittal: Online

  16. May 7, 2025

    Application filed

Documents

Site plans

  • Email thread in which the applicant says the project was cut to a deck with no retaining walls to seek a Category I hillside rating, and lists the items requested by the city.

    June 10, 2026 · 3 pages · 322 KB · PDS-Other Small Docs

    Download Updated scope of work email, reduced deck-only project
  • Scaled site plan sheet showing the proposed patio's edge, retaining wall, steps, and finished floor elevations relative to the existing residence and AC pad.

    June 6, 2025 · 1 page · 14.9 MB · PDS-Other Small Docs

    Download Site plan showing size and location of proposed patio
  • May 7, 2025 · 1 page · 489 KB · PDS-Other Small Docs

    Download Site plan

Plans

  • Revised deck plan and foundation and framing sheets for a residential deck, with a sheet index listing the deck plans and deck sections and 3D views.

    May 18, 2026 · 1 page · 251 KB · PDS-Other Small Docs

    Download Updated deck drawings

Project narrative

  • Advisory concept review notes: project reclassified as a Category II Hillside project, with a geotechnical report and possible slope stability analysis expected; scope later reduced to a deck with no new walls.

    June 2, 2026 · 3 pages · 468 KB · PDS-Concept Review Summary Report

    Download Concept review summary for hillside porch addition
  • Advisory concept review summary for a Category II hillside project proposing a porch addition and retaining walls, with notes on required geotechnical and structural documents.

    May 20, 2026 · 3 pages · 468 KB · PDS-Concept Review Summary Report

    Download Concept review summary report
  • Advisory concept review summary determining the hillside project is Category II due to proposed retaining wall heights, and listing additional documents likely needed for review.

    June 23, 2025 · 1 page · 443 KB · PDS-Concept Review Summary Report

    Download Concept review summary report

Studies and reports

  • Geotechnical investigation by ABCO Engineering covering site reconnaissance, field explorations, subsurface profile, ground motion, corrosion potential, and earthwork recommendations.

    May 7, 2025 · 52 pages · 2.5 MB · PDS-Other Small Docs

    Download Geotechnical investigation report

Correspondence

  • Public Works guidance on when retaining walls in the hillside zone need a determination, slope stability analysis, and planning-code height and setback limits.

    May 19, 2026 · 5 pages · 804 KB · PDS-Agency Comments

    Download Hillside retaining wall permitting guidance

Other documents

  • Checklist asking whether the project involves new parcel lines, additions, new dwellings, driveways, deep grading, or retaining walls, with yes/no/unknown answers.

    May 18, 2026 · 1 page · 309 KB · PDS-Other Small Docs

    Download Public Works hillside project questionnaire (updated)
  • Application form

    May 7, 2025 · 154 KB · PDS-Application

  • Public Works questionnaire answering whether the project involves new grading over 12 inches deep and retaining walls, with other hillside-related items marked no.

    May 7, 2025 · 1 page · 698 KB · PDS-Other Small Docs

    Download Hillside project questionnaire

Nearby

The Boise Builds daily briefing

Every new planning application in the Treasure Valley, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.