Idaho Power substation design approved by Eagle City Council
The council approved on consent the design review for a 7-acre public service facility, an Idaho Power substation, on land applicant GWC Capital requested it for. The decision was July 9, 2024.
Location
The filing doesn't give an address or parcel number, so it isn't on the map.
The 7-acre (approximate) site is located near the future northwest corner of Aerie Way and Willow Creek Road (Ada County Assessor parcel number S0218212700) which is outside of the PUMP No. 1 boundary but is considered an essential public facility.From the filing’s description
From the filing
The application's description as it appears in City of Eagle's record. See the official record
GWC Capital asked for design review approval to build an Idaho Power electric substation on about 7 acres near the future northwest corner of Aerie Way and Willow Creek Road in Eagle. The fenced substation pad would sit into an existing slope, screened by berms, with a gravel access road and a driveway to Aerie Way. The site is undeveloped range land in the Valnova development.
GWC Capital, represented by Eric Langvardt with Langvardt Design Group, is requesting design review approval of a public service facility for an Idaho Power substation. The 7-acre (approximate) site is located near the future northwest corner of Aerie Way and Willow Creek Road (Ada County Assessor parcel number S0218212700) which is outside of the PUMP No. 1 boundary but is considered an essential public facility.
Project name on file: Public Service Facility for an Idaho Power Substation
Timeline
July 9, 2024
Approved
Eagle City Council: Approved on its consent agenda.
Documents
Staff reports
- Idaho Power substation design review
July 8, 2024
Decisions
- Findings for design review of Idaho Power substation