Subdivision · Planning application
Approved: 13 homes planned on 4 acres in Meridian subdivision
The city approved the final plat for Sky Mesa Commons No. 5, a residential subdivision with 13 building lots and one common lot. The decision was made on March 23, 2021, and the plat has since been finaled.
From the filing
The application's description as it appears in City of Meridian's record. See the official record
Final Plat for residential subdivision with 13 residential lots and 1 common lot on 4 acres in R-8
Project name on file: Sky Mesa Commons No.5
Timeline
March 24, 2021
Application Complete: Done
March 24, 2021
Final Action: Application Complete
Order Signed 3-23
March 23, 2021
Public hearing: Meridian City Council
Outcome: Order Approved.
March 23, 2021
Decision: Order Approved
Meridian City Council: Order Approved.
March 9, 2021
Public hearing: Meridian City Council
March 2, 2021
Public hearing: Meridian City Council
Feb. 24, 2021
Application Complete: Done
Feb. 24, 2021
City Council Hearing: Approved
Feb. 24, 2021
Planning and Zoning Hearing: Bypass Planning and Zoning
Feb. 24, 2021
Parks Review: No Comment
Feb. 23, 2021
Public hearing: Meridian City Council
Feb. 16, 2021
Public hearing: Meridian City Council
Feb. 10, 2021
Application Complete: Done
Feb. 10, 2021
Community Development Review: Staff Recommend Approval w/ Cond
Jan. 29, 2021
Application Complete: Done
Jan. 29, 2021
Transportation Plan Review: Review Complete w/ Cond
Streetlight plan needs to be on a stand alone drawing pursuant to section 6 of the Meridian Design Standards and Meridian Supplemental Specifications.
Jan. 27, 2021
Application Complete: Done
Jan. 27, 2021
Water Modeling Review: Review Complete
See Engineering-Water Staff Report Comments
Jan. 26, 2021
Application Complete: Done
Jan. 26, 2021
Reclaimed Water Review: Connection NOT required
Jan. 26, 2021
Floodplain Review: FLDP Not Required
Jan. 26, 2021
Wastewater Modeling Review: Review Complete
See Engineer-WW Staff Report Comments
Jan. 26, 2021
MPD Review: No Comment
Jan. 26, 2021
GIS Review: Review Complete
Jan. 26, 2021
MFD Plan Review: Review Complete
Jan. 26, 2021
Transmit and Notice: Distribute for Plan Review
Jan. 25, 2021
Application Complete: Done
Jan. 25, 2021
Plan Intake: Accepted
Jan. 12, 2021
Application Complete: Done
Jan. 12, 2021
Plan Intake: More Information Required
Just need final street name approval letter
Jan. 8, 2021
Application Complete: Done
Jan. 8, 2021
Plan Intake: More Information Required
emailed Wendy on 1/8:Please submit the following:• a final street name approval letter for this phase (the one submitted is for phases 1 and 2).• an emergency access exhibit (per Joe)
Jan. 5, 2021
Application Complete: Done
Jan. 5, 2021
Planning Cursory Review: Return to Plan Intake
Jan. 5, 2021
Plan Intake: Application Submitted
Jan. 4, 2021
Application Complete: Done
Jan. 4, 2021
Reclaimed Water Review: Connection NOT required
Jan. 4, 2021
GIS Cursory Review: Entered in GIS
Jan. 4, 2021
Plan Intake: Cursory Review
Dec. 31, 2020
Application Complete: Done
Dec. 31, 2020
Plan Intake: Application Submitted
Dec. 30, 2020
Application Complete: Done
Dec. 30, 2020
Plan Intake: Application Incomplete
waiting for items entitled Final Plat, Signature Sheet, and Construction Drawings.
Dec. 30, 2020
Application filed
Documents
Staff reports
- Engineering water division staff report comments
Jan. 27, 2021 · 19 KB · Viewable by All
- Engineering staff report comments on wastewater
Jan. 26, 2021 · 14 KB · Viewable by All
Correspondence
- Email confirmation of final action courtesy letter
March 24, 2021 · 149 KB · Viewable by All
Other documents
- Sky5 archive
Dec. 30, 2020 · 17.7 MB · Viewable by All