Approved: 83 building lots and 75 homes planned on 132 acres in Ten Mile Crossing
The City Council approved a master development agreement, rezoning of several parcels, and a preliminary plat for 83 buildable lots and two common lots on 132.42 acres. The plan covers residential, commercial, employment and multi-family uses.
From the filing
The application's description as it appears in City of Meridian's record. See the official record
MDA to replace all existing DA's in the TM Crossing area with one Master DA with project specific design guidelines; Rezone of 40.98 from R-40 & C-C to C-G, 3.9 from TN-C & C-G to R-40, 0.65 from R-8 & TN-C to C-G and 0.53 from TN-C to C-G; and PP for 83 buildable lots & 2 common on 132.42 acres. S1214120661; S1214120710; S1214121133; S1214121134; S1214121172; S1214212580; S1214212622; S1214212742; S1214120631; S1214212805; S1214212822; S1214233668; S1214234021; S1214233680
Project name on file: Ten Mile Crossing/TM Center
Timeline
Jan. 13, 2022
Application Complete: Done
Task closed by script.
Jan. 13, 2022
GIS Final Review: No Comment
June 8, 2021
Public hearing: Meridian City Council
Outcome: Approved.
June 8, 2021
Decision: Approved
Meridian City Council: Approved.
May 12, 2021
Final Action: Application Complete
May 11, 2021
Public hearing: Meridian City Council
Outcome: FF-CL Requested for Approval.
May 11, 2021
Decision: FF-CL Requested for Approval
Meridian City Council: FF-CL Requested for Approval.
April 27, 2021
Public hearing: Meridian City Council
Outcome: FF-CL Requested for Approval.
April 27, 2021
Decision: FF-CL Requested for Approval
Meridian City Council: FF-CL Requested for Approval.
April 15, 2021
City Council Hearing: Approved
April 13, 2021
Public hearing: Meridian City Council
March 19, 2021
Planning and Zoning Hearing: Recommend Approval
March 18, 2021
Public hearing: Meridian Planning and Zoning Commission
Outcome: Recommended Approval.
March 18, 2021
Recommended Approval
Meridian Planning and Zoning Commission: Recommended Approval.
Jan. 21, 2021
Public hearing: Meridian Planning and Zoning Commission
Dec. 4, 2020
Application Complete: Done
Dec. 4, 2020
Planning and Zoning Hearing: Continued
Dec. 3, 2020
Public hearing: Meridian Planning and Zoning Commission
Sept. 18, 2020
Application Complete: Done
Sept. 18, 2020
Planning and Zoning Hearing: Continued
Sept. 17, 2020
Public hearing: Meridian Planning and Zoning Commission
Aug. 10, 2020
Application Complete: Done
Aug. 10, 2020
Community Development Review: Staff Recommend Approval w/ Cond
Aug. 6, 2020
Public hearing: Meridian Planning and Zoning Commission
Aug. 3, 2020
Application Complete: Done
Aug. 3, 2020
Parks Review: Review Complete w/ Cond
uploaded
July 6, 2020
Application Complete: Done
July 6, 2020
MFD Plan Review: Review Complete w/ Cond
Comments uploaded to Accela and emailed to the clerk.
July 1, 2020
Application Complete: Done
July 1, 2020
Reclaimed Water Review: Connection NOT required
Connection not required.
July 1, 2020
MPD Review: Review Complete w/ Cond
See police comments sent to clerks office Chris Johnson 7/1/20
June 26, 2020
Application Complete: Done
June 26, 2020
Water Modeling Review: Review Complete
See both the water markup and Engineering-Water Staff Report Comments
June 26, 2020
Transportation Plan Review: Review Complete w/ Cond
A street light plan will need to be included in the final plat application. Street light plan requirements are listed in section 6-7 of the City's Design Standards.
June 25, 2020
Application Complete: Done
June 25, 2020
Floodplain Review: FLDP Not Required
June 25, 2020
Wastewater Modeling Review: Review Complete
See Engineering-WW Staff Report Comments
June 25, 2020
GIS Review: Review Complete
June 25, 2020
Transmit and Notice: Distribute for Plan Review
June 25, 2020
Plan Intake: Accepted
June 18, 2020
Application Complete: Done
June 18, 2020
Reclaimed Water Review: Connection NOT required
Connection Not Required.
June 17, 2020
Application Complete: Done
June 17, 2020
Planning Cursory Review: Return to Plan Intake
June 17, 2020
GIS Cursory Review: Entered in GIS
June 17, 2020
Plan Intake: Application Submitted
June 16, 2020
Application Complete: Done
June 16, 2020
Plan Intake: Cursory Review
June 16, 2020
Application filed
Documents
Site plans
- Pre-plat
June 16, 2020 · 5.5 MB · Viewable by All
Plans
- Water markup
June 26, 2020 · 1.3 MB · Viewable by All
- Building elevations
June 16, 2020 · 4.1 MB · Viewable by All
- Landscape plan
June 16, 2020 · 3.0 MB · Viewable by All
- Pathway plan
June 16, 2020 · 584 KB · Viewable by All
- Phasing plan
June 16, 2020 · 259 KB · Viewable by All
Staff reports
- Engineering water staff report comments
June 26, 2020 · 18 KB · Viewable by All
- Engineering staff report comments
June 25, 2020 · 12 KB · Viewable by All
Studies and reports
- Geotechnical report
June 16, 2020 · 1.7 MB · Viewable by All
Correspondence
- Email confirmation of final action courtesy letter
May 21, 2021 · 151 KB · Viewable by All
- Pathways comments
Aug. 3, 2020 · 51 KB · Viewable by All
- Sewer comment
June 25, 2020 · 1.3 MB · Viewable by All
Other documents
- Legal description for rezoning to C-G, north parcel
March 12, 2021 · 1.0 MB · Viewable by All
- Legal description for rezoning to C-G (south)
March 12, 2021 · 1.8 MB · Viewable by All
- Legal description for rezone to R-40
March 12, 2021 · 1.0 MB · Viewable by All
- AutoCAD file
June 16, 2020 · 6.9 MB · Viewable by All