Conditional use (time extension) · Planning application
Time extension approved for 1,965-acre solar farm and substation
Ada County staff approved a time extension on Jan. 12 for earlier approvals covering a solar power facility, electric transmission line and substation on about 1,965 acres.
From the filing
The application's description as it appears in Ada County's record. See the official record
Administrative Time Extension for an approved Variance, Conditional Use, Master Site Plan, and Private Road for a Centralized Power Facility (Solar Farm), Electric Transmission Line, and Substation. The property is generally located northeast of Blacks Creek Rd and Interstate 84 and contains approximately 1,965 acres in the Rural Preservation (RP) District; Sections 15, 16, 22, 23, 27 & 27, T.2N, R.3E.
Timeline
Jan. 12, 2026
Approved
Approved by Ada County Development Services staff.
Dec. 22, 2025
Application filed
Documents
No documents have been published for this record yet.