Master site plan (modification) · Planning application
Approved: solar facility can be built before battery storage on 4,323 acres
Ada County staff approved a one-year extension of conditions for the site and let construction of the solar facility start before the battery storage facility. The decision was made Dec. 5.
From the filing
The application's description as it appears in Ada County's record. See the official record
An Administrative Modification and Time Extension for approval to extend the Conditions of approval deadline one year and to allow for construction on the Solar Facility prior to constructing the Battery Storage Facility. The property is generally located southwest of Interstate 84, between the Eisenman Rd and Blacks Creed Rd interchanges on 4,323 acres in the Rural Preservation (RP) District; Section XX, T.XX, R.XX.
Timeline
Dec. 5, 2025
Approved
Approved by Ada County Development Services staff.
Oct. 24, 2025
Application filed