Conditional use · Planning application
Conditional use permit approved
Conditional Use and Master Site Plan for a Centralized Power Facility (Solar Farm), Electric Transmission Line, Battery Energy Storage System and Substation. Also included is a Variance to maximum site coverage.
From the filing
The application's description as it appears in Ada County's record. See the official record
Conditional Use and Master Site Plan for a Centralized Power Facility (Solar Farm), Electric Transmission Line, Battery Energy Storage System and Substation. Also included is a Variance to maximum site coverage. The property is generally located north of Kuna Mora Rd and east of S Cole Rd and contains approximately 2,600 acres in the Rural Preservation (RP) District; Sections 27, 28, 29, 30, 31, 32, 33, 34, 35, T.2N, R.2E and Section 3, T.1N, R.2E.
Timeline
Dec. 30, 2025
Approved
Ada County Board of County Commissioners: Approved.
Dec. 30, 2025
Public hearing: Ada County Board of County Commissioners
Dec. 10, 2025
Ada County staff recommended approval
Dec. 10, 2025
Public hearing: Ada County Board of County Commissioners
Dec. 5, 2025
Document added: Memo (Board of County Commissioners, Dec 10, 2025)
Dec. 3, 2025
Document added: Staff report (Board of County Commissioners, Dec 10, 2025)
Dec. 3, 2025
Document added: Findings (Board of County Commissioners, Dec 10, 2025)
Aug. 12, 2025
Application filed
Documents
Other documents
- Memo (Board of County Commissioners, Dec 10, 2025)
Dec. 5, 2025 · 345 KB · Staff Memo
- Staff report (Board of County Commissioners, Dec 10, 2025)
Dec. 3, 2025 · 103.3 MB · Staff Report
- Findings (Board of County Commissioners, Dec 10, 2025)
Dec. 3, 2025 · 366 KB · Findings