Development review · Planning application
Fire station expansion with new sleep room and fitness room approved
The approved plans add one sleep room to Meridian Fire Station 3 and remodel the inside, including a new office, shop, decontamination room and bunker gear room. A new concrete fitness patio is also included on the 0.78-acre site.
From the filing
The application's description as it appears in City of Meridian's record. See the official record
Addition of (1) new sleep room. Interior alterations include shared work area, new office, relocation of (1) existing restroom, new fitness room, new bunker gear room, new decon room, and new shop. New exterior fitness concrete patio. Narrative will be uploaded along with drawings.
Project name on file: Meridian FS 3
Timeline
June 18, 2026
Transportation Plan Review: No Comment
June 16, 2026
MPD Review: Approved
June 15, 2026
MFD Plan Review: Approved
June 10, 2026
Planning Review: Approved
June 9, 2026
Wastewater Modeling Review: Approved
June 8, 2026
Water Modeling Review: Approved
June 8, 2026
GIS Review: Approved
June 5, 2026
ACHD Review: Approved
June 5, 2026
Land Development Review: No Comment
June 1, 2026
Floodplain Review: FLDP Not Required
June 1, 2026
Application Submittal: Accepted
sending through for review at request of Nick N
May 29, 2026
Application Submittal: More Information Required
The following uploads are required for a CZC/DES permit application per the submittal standards. Some of these items might be in your full packet, but we require them to be broken out and uploaded separately and named per submittal standards. Drawings: Vicinity MapTrash Enclosure Approval Photometric PlanRecord PlatLandscape PlanElevationsDocuments: Warranty DeedAffidavit of Legal InterestASM Checklist
May 29, 2026
Application filed
Documents
No documents have been published for this record yet.