Subdivision · Planning application

68-lot subdivision approved

56 residential lots, 12 commercial lots,

ApprovedFP-2021-0004Filed Jan. 14, 2021Southeast Meridian · 6575 Locust Grove+2 related filings
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

From the filing

The application's description as it appears in City of Meridian's record. See the official record

56 residential lots, 12 commercial lots,

Project name on file: Apex Northwest No. 1 FP

Timeline

  1. March 24, 2021

    Application Complete: Done

  2. March 24, 2021

    Final Action: Application Complete

    Order Signed on 3-17

  3. March 24, 2021

    City Council Hearing: Approved

  4. March 24, 2021

    Planning and Zoning Hearing: Bypass Planning and Zoning

  5. March 22, 2021

    Application Complete: Done

  6. March 22, 2021

    Parks Review: Review Complete

    Pathways depicted per PP Conditions

  7. March 16, 2021

    Public hearing: Meridian City Council

    Outcome: Order Approved.

  8. March 16, 2021

    Decision: Order Approved

    Meridian City Council: Order Approved.

  9. March 2, 2021

    Public hearing: Meridian City Council

  10. Feb. 24, 2021

    Application Complete: Done

  11. Feb. 24, 2021

    Community Development Review: Staff Recommend Approval w/ Cond

  12. Feb. 5, 2021

    Application Complete: Done

  13. Feb. 5, 2021

    MPD Review: No Comment

  14. Feb. 5, 2021

    Water Modeling Review: Review Complete

    See Engineering - Water Staff Report Comments

  15. Feb. 5, 2021

    Transportation Plan Review: Review Complete w/ Cond

    Streetlights on internal roads appear to meet requirements. Streetlights are required on Locust Grove and Lake Hazel prior to occupancy within the subdivision. Streetlight plan for Lake Hazel and Locust Grove is required with the road improvement drawings.

  16. Feb. 4, 2021

    Application Complete: Done

  17. Feb. 4, 2021

    Reclaimed Water Review: Connection NOT required

  18. Feb. 4, 2021

    Floodplain Review: FLDP Not Required

  19. Feb. 4, 2021

    Wastewater Modeling Review: Review Complete

    See Engineering-WW Staff Report Comments

  20. Feb. 4, 2021

    GIS Review: Review Complete

  21. Feb. 4, 2021

    MFD Plan Review: Review Complete

  22. Feb. 4, 2021

    Transmit and Notice: Distribute for Plan Review

  23. Feb. 3, 2021

    Application Complete: Done

  24. Feb. 3, 2021

    Plan Intake: Accepted

  25. Feb. 2, 2021

    Application Complete: Done

  26. Feb. 2, 2021

    Plan Intake: More Information Required

    emailed Kody on 2/2:The updated warranty deed states that SCS Investments LLC and DWT Investments LLC each own 50% interest in the property; therefore, I also need an affidavit from SCS. Also, please submit Articles of Incorporation for both business entities that verify who the authorized signer is for each business per the application checklist. Please revise the narrative to exclude the alternative compliance request to UDC 11-6C-3B.53 as alleys aren’t eligible for Alternative Compliance per UDC Table 11-5B-5. The ALT request for the common driveways should cover it.

  27. Jan. 19, 2021

    Application Complete: Done

  28. Jan. 19, 2021

    Planning Cursory Review: Return to Plan Intake

  29. Jan. 19, 2021

    Plan Intake: Application Submitted

  30. Jan. 19, 2021

    Plan Intake: More Information Required

    emailed Kody on 1/19:I’ve reviewed your application and need the following additional items:• Evidence showing that Robert Phillips, Brighton Investments, LLC is an authorized agent to sign the affidavit of legal interest for Tomlinson Family Trust per the application checklist. • In the Application section of your narrative, include file #H-2020-0066 as the file # associated with the rezone Ordinance (#20-1910, recorded as Inst. #2020-178119) and DA (Inst. #2020-178120). (not sure what the “Z”’s are for…)• In the narrative for the alternative compliance (ALT) request, address which conditions listed in UDC 11-5B-5B.2 exist for which ALT should be approved; and also address how the proposed alternative means of compliance provides and equal or superior means of meeting the intent and purpose of the regulation as required by 11-5B-5D.

  31. Jan. 15, 2021

    Application Complete: Done

  32. Jan. 15, 2021

    GIS Cursory Review: Entered in GIS

  33. Jan. 14, 2021

    Application Complete: Done

  34. Jan. 14, 2021

    Reclaimed Water Review: Connection NOT required

  35. Jan. 14, 2021

    Plan Intake: More Information Required

    emailed Kody for narrative sheet

  36. Jan. 14, 2021

    Plan Intake: Application Submitted

  37. Jan. 14, 2021

    Plan Intake: Cursory Review

  38. Jan. 14, 2021

    Application filed

Documents

Other documents

  • 20-155 Landscape Certification Letter.pdf

    Dec. 4, 2025 · 207 KB · Viewable by All

  • Engineering-Water Staff Report Comments_KK

    Feb. 5, 2021 · 19 KB · Viewable by All

  • Engineering-WW Staff Report Comments_TG

    Feb. 4, 2021 · 14 KB · Viewable by All

  • Alternative Compliance App

    Jan. 14, 2021 · 9.6 MB · Viewable by All

  • Final Plat App.7z

    Jan. 14, 2021 · 87.0 MB · Viewable by All

Nearby

The Boise Builds daily briefing

Every new planning application in the Treasure Valley, and every filing that changed, in one email each morning. See a sample

Free. One email a day, only when something is new. Unsubscribe anytime.