Approved: 72,419-square-foot metalwork shop and office building on 6.67 acres
Ada County's Planning and Zoning Commission approved the two-story fabrication and assembly shop with attached offices on Nov. 13, with conditions including limited hours, street widening and an airport avigation easement.
From the filing
The application's description as it appears in Ada County's record. See the official record
The applicant proposes an office and shop building for metalwork fabrication and assembly on four parcels at 4551, 4647, and 5907 S Henry St in Boise. The two-story building would total about 72,419 square feet on a 6.67-acre site. Planning staff recommends approval, and the Planning and Zoning Commission had not yet ruled when this report was written.
Conditional Use, Master Site Plan, and Floodplain for a metalwork fabrication and assembly shop and office building.The property is located at 4551, 4647 and 5907 S. Henry Street and contains 6.67 acres in the Airport Industrial (M3) District. Section 32, T.3N, R.2E.
Timeline
Nov. 13, 2025
Ada County staff recommended approval
Nov. 13, 2025
Approved
Ada County Planning and Zoning Commission: Approved.
Nov. 13, 2025
Public hearing: Ada County Planning and Zoning Commission
Nov. 5, 2025
Document added: Staff report (Planning and Zoning Commission, Nov 13, 2025)
Nov. 4, 2025
Document added: Findings (Planning and Zoning Commission, Nov 13, 2025)
Aug. 18, 2025
Application filed
Documents
Staff reports
- Download Staff report for Nov. 13 Planning and Zoning Commission hearing
Staff analysis recommending review of a conditional use, master site plan and floodplain permit for a metalwork fabrication office and shop, covering airport influence, building variation and flood hazard issues.
Nov. 5, 2025 · 110 pages · 54.1 MB · Staff Report
Decisions
- Download Findings of fact, conclusions of law and order
Planning and Zoning Commission findings and order for a conditional use application for a metalwork fabrication and assembly shop with an office, following the Nov. 13, 2025 hearing.
Nov. 4, 2025 · 13 pages · 344 KB · Findings