Design review · Planning application
CrossFit E3 gym and office building approved in Eagle
The Eagle Design Review Board approved plans for a two-story, 10,916-square-foot building housing an office and a CrossFit-style fitness use on a 0.95-acre lot, with conditions on a shared drive aisle, a landscape buffer and trash enclosure screening. The decision was made April 10.
From the filing
The application's description as it appears in City of Eagle's record. See the official record
CrossFit E3 wants to build a two-story, roughly 10,900-square-foot building for offices and a CrossFit-style fitness use at 2320 West Copper Silo Street in the Stillwater Subdivision. The building would sit on a 0.95-acre vacant lot with 45 parking spaces. The Design Review Board voted to approve it with conditions.
The .95-acre site is located on the north side of West Copper Silo Street approximately 150-feet west of South Urban Gate Avenue at 2320 West Copper Silo Street (Lot 2, Block 6, Stillwater Subdivision No. 1).
Project name on file: Office (Business and Professional) and Personal Improvement Building within Stillwater Subdivision
Timeline
April 10, 2025
Approved
Eagle Design Review Board: Approved. Findings adopted April 10, 2025.
Documents
Decisions
- Download Design review findings of fact and conclusions of law
The Eagle Design Review Board's March 27, 2025 findings approving or deciding the design review for the CrossFit E3 office and personal improvement building, a 10,916-square foot two-story structure.
April 9, 2025 · 18 pages · 1.2 MB · Decision