Rezone · Planning application
Stonehill Church's 40,453-square-foot building and four lots approved
The city approved a church on about 13 acres, along with a 13.36-acre rezone, a conditional use permit and a four-lot preliminary plat. The decision came at a hearing held March 26, 2024, and the project also modifies an older development agreement.
From the filing
The application's description as it appears in City of Meridian's record. See the official record
Hearing date: February 1, 2024 Request: Modification to the existing Development Agreement (H-2015-0019, Inst. #2016-007090) to allow for the development of a church on a portion of the property and removal of that property from the original agreement for inclusion in a new agreement; Rezone of 13.36-acres of land from the R-4 to the R-8 zoning district; Conditional use permit for a church on 13.09-acres of land in an R-8 zoning district; and Preliminary plat consisting of 4 building lots on 65.43-acres of land in the R-4 and R-8 zoning districts for Stonehill Crossing Subdivision, by Stonehill Church. Location: 799 W. Amity Rd., in the north 1/2 of Section 36, T.3N., R.1W.
Project name on file: Stonehill Church
Timeline
July 19, 2024
Application Complete: Done
July 19, 2024
GIS Final Review: Entered In GIS
April 1, 2024
Final Action: Application Complete
March 26, 2024
Public hearing: Meridian City Council
Outcome: Approved.
March 26, 2024
Decision: Approved
Meridian City Council: Approved.
March 13, 2024
City Council Hearing: Approved
March 12, 2024
Public hearing: Meridian City Council
Feb. 5, 2024
Planning and Zoning Hearing: Approved
Feb. 1, 2024
Public hearing: Meridian Planning and Zoning Commission
Outcome: Recommended Approval.
Feb. 1, 2024
Recommended Approval
Meridian Planning and Zoning Commission: Recommended Approval.
Jan. 12, 2024
Planning and Zoning Hearing: More Information Required
Jan. 3, 2024
Planning Review: Approved
Dec. 21, 2023
Planning Review: More Information Required
Dec. 14, 2023
Planning Review: More Information Required
Dec. 11, 2023
Planning Review: More Information Required
Oct. 5, 2023
Planning Review: More Information Required
Aug. 7, 2023
Transportation Plan Review: Approved
Aug. 4, 2023
Planning Review: More Information Required
Aug. 4, 2023
MFD Plan Review: Approved
Aug. 3, 2023
Land Development Review: Approved
Aug. 2, 2023
Property Owners List Review: Approved
Aug. 1, 2023
Wastewater Modeling Review: Approved
July 31, 2023
Parks Review: Approved
July 25, 2023
Water Modeling Review: Approved
July 24, 2023
ACHD Review: Approved
July 24, 2023
MPD Review: Approved
July 24, 2023
GIS Review: Approved
July 24, 2023
City Clerk Review: Approved
July 24, 2023
Legal Description Review: Approved
July 21, 2023
Reclaimed Water Review: Connection NOT required
July 21, 2023
Floodplain Review: FLDP Not Required
July 21, 2023
Application Submittal: More Information Required
Prescreen correction - narrative needed, RZ exhibit needed.
July 21, 2023
Application Submittal: Accepted
July 20, 2023
Application Submittal: More Information Required
Prescreen corrections - Missing documents - Narrative, warranty deed and RZ exhibit
July 20, 2023
Application filed
Documents
No documents have been published for this record yet.