Approved: 22,281-square-foot indoor hitting facility for Northwest Nazarene University
The city found the project did not meet the threshold requiring design review, so it was closed Oct. 3 as completed. The metal building would house a lobby, storage, restrooms and indoor practice space for baseball, softball and golf teams.
From the filing
The application's description as it appears in City of Nampa's record. See the official record
**After Reviewing the project submission, the scope of work does not meet the threshold to require Design Review.** The project is a 22,281 SF hitting facility for the Northwest Nazarene University. Metal building with metal lean-tos. Program includes lobby, storage, restrooms, and indoor hitting/practice space for Baseball, Softball, and Golf teams.
Project name on file: New hitting facility for Northwest Nazarene University.
Timeline
Oct. 3, 2024
12 documents added
Oct. 3, 2024
Decision: Approved
Sept. 27, 2024
Application filed
Documents
Site plans
- Site plan aerial
Sept. 27, 2024 · 804 KB · Site Plan
Renderings
- Hitting facility renderings
Sept. 27, 2024 · 21.0 MB · Building Finishes
Plans
- Hitting facility building elevations
Sept. 27, 2024 · 13.7 MB · Building Elevations
- NNU hitting facility building finishes
Building finishes sheet for the NNU hitting facility, listed under color samples for a design review application.
Sept. 27, 2024 · 7.6 MB · Color Samples
- Hitting facility floor plan
Sept. 27, 2024 · 183 KB · Other
- Landscape plan, sheet L1.0
Sept. 27, 2024 · 1.4 MB · Landscaping Plan
Project narrative
- Hitting facility narrative
Project narrative describing the proposed hitting facility for the NNU athletics site, submitted with the design review application.
Sept. 27, 2024 · 54 KB · Narrative
Correspondence
- Design review comments on the NNU hitting facility
Oct. 3, 2024 · 327 KB · Design Review not required
Other documents
- Design review checklist
Completed design review checklist for the NNU hitting facility, filed under the design review application for projects 5,000 square feet or greater.
Sept. 27, 2024 · Checklist & Master Application
- Material percentages and project specifics for NNU hitting facility
Document listing material percentages and project specifics for the NNU hitting facility, filed with the design review application.
Sept. 27, 2024 · Other
- Vicinity map
Sept. 27, 2024 · Vicinity Map
- Affidavit of legal interest
Affidavit of legal interest filed with the hitting facility permit application, dated Sept. 23, 2024.