Development review · Planning application

4,833-square-foot single-story office building approved

The approved plan covers two adjacent lots on about 1 acre. One gets the new office building, up to about 27 feet tall. The other gets a graded pad for a future office of roughly 3,500 square feet, plus shared parking and landscaping.

ApprovedA-2026-0087Filed June 24, 2026East Meridian · 195 Touchmark+1 related filing
Pin at the reported location; the shaded outline is the primary parcel (Ada County).

From the filing

The application's description as it appears in City of Meridian's record. See the official record

THE WORK WILL COVER TWO ADJACENT LOTS CURRENTLY UNDER THE SAME OWNERSHIP. CONSTRUCTION FOR LOT 12 WILL CONSIST OF A NEW OFFICE BUILDING, OF 4,833 S.F. GROSS FOOTPRINT. STRUCTURE WILL BE A SINGLE STORY WITH VOLUMES OF VARYING HEIGHTS, MAX. HEIGHT BEING APPROX. 27'. CONSTRUCTION FOR LOT 13 WILL CONSIST OF CREATING A CONSTRUCTION READY PAD FOR A FUTURE OFFICE BUILDING (APPROX. 3,500 S.F.). SITE DEVELOPMENT WILL COVER BOTH LOTS AND WILL COVER REQUIRED CIRCULATION AND AMENITIES LIKE SHARED ACCESS PARKING, LANDSCAPING AND TRASH ENCLOSURES TO ACCOMMODATE THE USE OF THE SITE.

Project name on file: Black Creek Legal Office

Timeline

  1. Sept. 4, 2026

    Water Modeling Review: Approved

  2. Sept. 4, 2026

    Planning Review: Approved

  3. Sept. 4, 2026

    Planning Review: More Information Required

  4. July 27, 2026

    MFD Plan Review: No Comment

  5. July 23, 2026

    Planning Review: More Information Required

  6. July 13, 2026

    MPD Review: Approved

  7. July 9, 2026

    Wastewater Modeling Review: Approved

  8. July 7, 2026

    Land Development Review: Approved

  9. July 6, 2026

    ACHD Review: Approved

  10. July 6, 2026

    Transportation Plan Review: No Comment

  11. July 6, 2026

    Water Modeling Review: More Information Required

  12. July 6, 2026

    GIS Review: Approved

  13. July 6, 2026

    Planning Review: More Information Required

  14. June 24, 2026

    Floodplain Review: FLDP Not Required

  15. June 24, 2026

    Application Submittal: More Information Required

    *Any highlighted checklist item above is required unless pre-authorized by a planner. If it is determined that a checklist item is not required, list the missing item(s) and planner’s name in the project description field in Accela. Public School Checklist*Autocad file*Public Utility Plan

  16. June 24, 2026

    Application Submittal: Accepted

  17. June 24, 2026

    Application filed

Documents

No documents have been published for this record yet.