Planned unit development · Planning application
Council approves 1,674 homes and 300,000 square feet of commercial space in Valnova
Clyde Capital Group's Valnova plan covers about 1,937 acres, with roughly 825 acres of open space and parks, and a possible 18-hole golf course. The Eagle City Council approved the plan on Dec. 10, 2024.
From the filing
The application's description as it appears in City of Eagle's record. See the official record
Clyde Capital Group asks the city to approve a master plan for part of the Valnova development (formerly Spring Valley), about 7,500 feet east of State Highway 16 at West Roseway Lane. The plan covers roughly 1,937 acres and proposes 1,674 homes, about 825 acres of open space and parks, 300,000 square feet of neighborhood-center commercial uses, and a possible 18-hole golf course.
Clyde Capital Group, represented by Eric Langvardt with Langvardt Design Group is requesting approval of Planning Unit Master Plan No. 5 for the Valnova Planned Development (formerly known as Spring Valley). Planning Unit Master Plan (PUMP) No. 5 consists of 1,936.82-acres of land within the Northern Residential and Big Gulch Planning Areas and is proposed to include 1,674 residential units, 824.96- acres of open space including community, neighborhood and pocket parks, community trails, 300,000 square feet of nonresidential Neighborhood Center uses, and potentially an 18-hole golf course, pursuant to the uses outlined within Eagle City Code Title 11A and in accordance with the amended and restated development agreement associated with the Valnova Development.
Project name on file: Valnova Planning Unit Master Plan (PUMP) No. 5
Timeline
Dec. 10, 2024
Approved
Eagle City Council: Approved. Findings adopted January 14, 2025.
Dec. 10, 2024
Public hearing: Eagle City Council
Nov. 18, 2024
Eagle Planning and Zoning Commission recommended approval
Nov. 4, 2024
Public hearing: Eagle Planning and Zoning Commission
Documents
Plans
- Compiled plan exhibits, PUMP No. 5
Dec. 9, 2024
- Compiled plan exhibits
Nov. 3, 2024
Staff reports
- Council packet for Valnova PUMP No. 5
Dec. 9, 2024 · Staff Report
- Planning and Zoning Commission packet
Nov. 3, 2024 · Staff Report
Decisions
- Download Findings of fact and conclusions of law for PUMP No. 5
Eagle City Council's findings and conclusions on Clyde Capital Group's request for Valnova Planned Unit Master Plan No. 5, covering 1,674 homes and 300,000 sq ft of neighborhood center uses.
Jan. 13, 2025 · 47 pages · 836 KB · Decision
- PUMP No. 5 findings
Nov. 17, 2024 · Decision
Studies and reports
- Exhibits A7-A8, fiscal impact analysis
Dec. 9, 2024
- Approved traffic impact study, PUMP No. 5
Approved traffic impact study for planning unit master plan No. 5, per the filename; no text was available to confirm details.
Dec. 9, 2024
- Fiscal impact analysis, exhibits A7-A8
Exhibits A7 and A8 to the Valnova planned unit master plan (PUMP No. 5), covering the fiscal impact analysis.
Nov. 3, 2024
- Approved traffic impact study, PUMP No. 5
Nov. 3, 2024