Planning project · Planning application
Plan to rebuild shopping center sidewalk and replace trees approved
The city approved the rebuilding of an internal sidewalk on a 5.65-acre commercial site on May 1. Existing trees would be replaced in new tree grates, with extra trees planted on-site to make up for lost trunk width. Parking and access stay unchanged.
From the filing
The application's description as it appears in City of Boise's record. See the official record
Rebuild existing internal sidewalk
Project name on file: 3614 W STATE ST
Timeline
May 1, 2026
Planning Applications: Project Entitled
March 23, 2026
Pending Application Submittal: Planning Applications in Review
March 20, 2026
Concept Review Complete: CR Complete - Type 2
Feb. 19, 2026
Application Submittal: Online
Feb. 19, 2026
Application filed
Documents
Project narrative
- Download Concept review summary
Planner notes on a March 12, 2026 concept review for a minor design review, covering sidewalk rebuild, tree replacement and a required arborist tree mitigation plan.
March 20, 2026 · 1 page · 458 KB · PDS-Concept Review Summary Report
- Download Concept review summary
Planner notes on a March 12, 2026 concept review for a minor design review, covering sidewalk rebuild, tree replacement and a required arborist tree mitigation plan.
March 20, 2026 · 1 page · 458 KB · PDS-Concept Review Summary Report
Application
- Download Planning project application form
Application by Brix Paving NW for removal of trees and sidewalk, grate and curb repairs to address pedestrian and ADA access damage.
Feb. 19, 2026 · 2 pages · 158 KB · PDS-Application
Studies and reports
- Download Tree evaluation plan for Albertsons store trees
Arborist addendum recommending removal of five honey locust trees damaged by roots and concrete, with photos and a map of the tree locations.
Feb. 19, 2026 · 6 pages · 1.1 MB · PDS-Other Small Docs